Tuesday, June 25, 2019

Segmental Retaining Wall Construction Time

A new contractor, homeowner or estimator may want to know how long it takes to construct a segmental block retaining wall. This answer depends on multiple factors including:

Site conditions
Site access
Wall layout (curves, bends, and obstructions)
Soil types (clayey soils may be more difficult to work with)
Contractor experience
Size of contractor crew
Equipment available

This is the general rule of thumb
100 sq ft per man per day
500 sq ft per crew per day
The base course will take the longest, assume
25 sq ft per man per day

No comments:

Post a Comment